Question #: 1218
Topic #: 1
[All PMP Questions]

A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?

  • A. Create a statement of work (SOW) and ensure it remains unchanged during the project life cycle.
  • B. Include project stakeholder expectations and needs while creating project acceptance criteria.
  • C. Schedule regular meetings with project stakeholders to make sure they are satisfied.
  • D. Discuss project acceptance criteria with the project sponsor before the execution phase.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Okstm
4 weeks, 1 day ago
Selected Answer: B
The most effective way to ensure that project acceptance criteria are met is to define them based on stakeholder needs and expectations from the start. This way, all deliverables will be evaluated against agreed-upon standards, leading to smoother acceptance processes.
upvoted 1 times
...
FasterN8
1 month, 3 weeks ago
Selected Answer: D
The question is about how to make sure criteria are met, not how to form them properly.
upvoted 1 times
...
victory108
2 months, 4 weeks ago
Selected Answer: B
B. Include project stakeholder expectations and needs while creating project acceptance criteria
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago