A project manager is leading a project at a contracting company, and the project team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

  • A. Follow the proper change control process and evaluate the change for further impact.
  • B. Perform frequent reviews with the customer to ensure that the product is working as expected.
  • C. Manage the scope baseline to influence the factors that drive change.
  • D. Work with the customer to ensure the feature adds value.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
1 month, 4 weeks ago
Selected Answer: A
A. Follow the proper change control process and evaluate the change for further impact
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...