exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 369 discussion

Actual exam question from PMI's CAPM
Question #: 369
Topic #: 1
[All CAPM Questions]

An agile team will begin to work on a project for a local conference. The team will deliver an information system with complete audience information, which includes many requirements. In order to begin working on the project, the team produces a checklist for a user-centric requirement that is needed to deliver the system.

Which checklist will the team produce?

  • A. Definition of done (DoD)
  • B. Definition of ready (DoR)
  • C. Product backlog
  • D. Sprint backlog
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
reve6669
2 days, 10 hours ago
Selected Answer: B
correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago