exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 361 discussion

Actual exam question from PMI's CAPM
Question #: 361
Topic #: 1
[All CAPM Questions]

A project manager was assigned to a project to implement a manufacturing system in a food factory. The main project objective is to deliver machines that are ready to process food. The project manager decides that this particular project does not require the use of timeboxed iterations.

Which method should the project manager adopt?

  • A. Scrum
  • B. SAFe
  • C. Feature-driven development (FDD)
  • D. Kanban
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
reve6669
2 days, 11 hours ago
Selected Answer: D
Correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago