A project manager is working on project cost management. The following information is current:

• Planned value = 30
• Actual cost = 35
• Earned value = 28

Considering this data, which project indicator is correct?

  • A. Schedule Variance (SV) = 2
  • B. Cost Performance Index (CPI) = 0.80
  • C. Schedule Performance Index (SPI) = 1.93
  • D. Cost Variance (CV) = 7
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
sentaayana
2 months, 1 week ago
CPI = EV/AC = 28/35= 0.8
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...