Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1225 discussion

Actual exam question from PMI's PMP
Question #: 1225
Topic #: 1
[All PMP Questions]

A project manager is assigned to a yearlong project. Before the start of the design phase, a competitor announces that they will release a similar deliverable in 8 months, although with fewer features and functionality.

Which two actions should the project manager take next? (Choose two.)

  • A. Modify the project management plan with an incremental approach.
  • B. Discuss and review this external risk with the project sponsor.
  • C. Update the project artifacts to include this issue.
  • D. Evaluate the impact of incremental deliverables.
  • E. Reduce the scope items of the final deliverable.
Show Suggested Answer Hide Answer
Suggested Answer: BD 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
d370e49
1 week ago
Selected Answer: BD
First 2 actions should be Discuss and Evaluate
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...