Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1411 discussion

Actual exam question from PMI's PMP
Question #: 1411
Topic #: 1
[All PMP Questions]

A developer who has almost completed a required product feature for a prototype leaves the company in the middle of an iteration. What should the project manager do?

  • A. Go to management and ask to hire a new external developer.
  • B. Review the backlog to reschedule the deliverable for a later iteration.
  • C. Determine whether other cross-functional team members are able to take over the work.
  • D. Engage with stakeholders directly to review the iteration process.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
funmis4
1 week, 6 days ago
Selected Answer: C
That is why a cross functional team is good for projects .part of the advantages of cross functional teams is to breakdown silos to foster collaboration and better communication. I guess someone on the team would have an idea and carry on the work but the event should be recorded in the log
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...