Exam PMP topic 1 question 1149 discussion

Actual exam question from PMI's PMP
Question #: 1149
Topic #: 1
[All PMP Questions]

A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?

  • A. Ask the project sponsor to inform the client in the next update.
  • B. Do not disclose the likelihood of a delay as it is yet to happen.
  • C. Work with the project team to evaluate the potential delay.
  • D. Tell the client about the chance for the potential delay.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
2 weeks, 4 days ago
Selected Answer: C
Always evaluate with your team members before meeting with stakeholders.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...