Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1341 discussion

Actual exam question from PMI's PMP
Question #: 1341
Topic #: 1
[All PMP Questions]

A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

  • A. Assign a qualified team member to be the risk manager for the project.
  • B. Remove the user stories associated to that risk and avoid the impact to the project deliverables.
  • C. Submit a change request to transfer the risk to a third party in case it becomes an issue.
  • D. Ask the team to monitor the risk and provide an alert if it becomes an issue.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
funmis4
2 weeks, 4 days ago
The entire should look out for risks
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...