Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1405 discussion

Actual exam question from PMI's PMP
Question #: 1405
Topic #: 1
[All PMP Questions]

A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations. Each user story is worth US$50. The actual expenditure is US$2,000 and 50 user stories have been delivered.

Which statement is true?

  • A. The project is under budget and on schedule.
  • B. The project is over budget and behind schedule.
  • C. The project is under budget and behind schedule.
  • D. The project is on budget and on schedule.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
funmis4
1 week, 5 days ago
5 iterations- that means an assumption of 100/5 =20 per each iteration . The budget then is $50 x 100 = $5,000 So if the question says at the middle of the project only $2000 has been expended , then it is under the budget @ $50 per user story
upvoted 2 times
...
Kim222
3 weeks, 3 days ago
Selected Answer: C
This is C
upvoted 1 times
d370e49
1 week ago
Explain your reasoning.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...