Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1280 discussion

Actual exam question from PMI's PMP
Question #: 1280
Topic #: 1
[All PMP Questions]

According to the project contract, the delivery date is approaching. However, one important material is still not on site. The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

  • A. Engage the project team to look for alternatives to find a solution.
  • B. Record it in the risk register.
  • C. Ask the client to help solve the problem.
  • D. Start procuring this material from another supplier.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: A
A. Engage the project team to look for alternatives to find a solution
upvoted 1 times
...
sidje
3 months ago
"Engagez l’équipe "
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...