Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1414 discussion

Actual exam question from PMI's PMP
Question #: 1414
Topic #: 1
[All PMP Questions]

A project manager’s transformation project has been delayed due to unexpected issues with the information technology (IT) systems. These issues are likely to impact the project budget, but the project manager is working hard to make ensure there is no impact on the project's schedule and scope.

Which two actions should the project manager take before proposing a budget rebaseline to upper management for approval? (Choose two.)

  • A. Consider schedule compression techniques to shorten or accelerate the schedule duration without reducing the project scope.
  • B. Consider using resource leveling to more accurately reflect the work commitments of the resources.
  • C. Apply data analysis techniques, variance analysis, and trend analysis.
  • D. Analyze the budget based on the revised estimates and responses from similar situations in the past.
  • E. Raise a change request with high priority to be discussed in the upcoming governance meetings.
Show Suggested Answer Hide Answer
Suggested Answer: CE 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
d370e49
1 week ago
Selected Answer: CD
I think it's C and D here. Why would you use a change request?
upvoted 1 times
...
Kim222
1 month, 1 week ago
Selected Answer: CD
I Think C,D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...