A project manager’s transformation project has been delayed due to unexpected issues with the information technology (IT) systems. These issues are likely to impact the project budget, but the project manager is working hard to make ensure there is no impact on the project's schedule and scope.
Which two actions should the project manager take before proposing a budget rebaseline to upper management for approval? (Choose two.)
MonBouj
1 month agovictory108
1 month, 1 week agoNgho
1 month, 2 weeks agod370e49
2 months, 1 week agoKim222
3 months, 2 weeks ago