The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them.

What should the project manager do first in this situation?

  • A. Provide the specifications to the project sponsor with some information removed.
  • B. Update the issue log to make the project team aware and to develop a strategy.
  • C. Create a stakeholder engagement plan to help the team formulate a response.
  • D. Meet with the project sponsor as soon as possible to discuss the matter further.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Hamiakz
1 month ago
Selected Answer: D
By meeting with the project sponsor, the project manager can maintain transparency, build trust, and work towards a solution that respects both the sponsor’s needs and the project’s governance policies.
upvoted 1 times
...
Kim222
1 month, 1 week ago
Selected Answer: D
In PMP, the sponsor is GOD. If the person wants it, you have to find a reason.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...