Question #: 1139
Topic #: 1
[All PMP Questions]

DRAG DROP
-

A project manager is working on a complex project and is unsure about planning, executing, monitoring and controlling the project. Match the phrase on the left with the correct statement on the right.

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 1 day ago
Risks and costs --> are controlled as requirements and constraints emerge. Requirements --> are elaborated frequently during delivery. Changes --> are incorporated in real-time during delivery. Key stakeholders --> are continuously engaged throughout delivery.
upvoted 1 times
...
Mgaidiwahid
1 month, 2 weeks ago
Correct for me !
upvoted 1 times
...
Kim222
3 months, 2 weeks ago
alright
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...