exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1390 discussion

Actual exam question from PMI's PMP
Question #: 1390
Topic #: 1
[All PMP Questions]

After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?

  • A. Ahead of schedule
  • B. On schedule
  • C. Behind schedule
  • D. Stopped
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nimitto
4 weeks, 1 day ago
Selected Answer: C
Behind Schedule
upvoted 1 times
...
MonBouj
2 months ago
Selected Answer: C
C. Behind schedule Schedule variance refers to the difference between the work that has been completed and the work that was planned at a given point in time. A negative schedule variance indicates that less work has been completed than was planned, meaning the project is behind schedule. Even though the project is under budget and quality checks are positive, a negative schedule variance shows that the project is not progressing as planned in terms of time.
upvoted 1 times
...
victory108
2 months, 1 week ago
Selected Answer: C
C. Behind schedule
upvoted 1 times
...
Ngho
2 months, 3 weeks ago
C. Behind schedule The project manager mentions that the schedule variance is negative, which indicates that the project is behind schedule. Even though the project is under budget and quality checks are positive, a negative schedule variance specifically points to delays in the timeline.
upvoted 1 times
...
Ayomidetolu_A
3 months, 1 week ago
A negative schedule variance means the project is behind schedule. Answer is C
upvoted 1 times
...
d370e49
3 months, 1 week ago
Selected Answer: C
Are you people voting for A really serious? "A negative SV indicates your project is behind schedule" The answer is C!
upvoted 1 times
...
nealmukundan
3 months, 3 weeks ago
Selected Answer: A
In project management, a negative schedule variance means that the project is ahead of schedule. So, the project manager should qualify the project status as: A. Ahead of schedule
upvoted 1 times
d370e49
3 months, 1 week ago
Incorrect, you have it all backwards
upvoted 1 times
...
...
Rayeigh
4 months, 2 weeks ago
Selected Answer: C
I would change my answer. SV = EV - PV. SV is negative, It means behind.
upvoted 1 times
...
Rayeigh
4 months, 2 weeks ago
Selected Answer: A
I think A is correct.
upvoted 1 times
d370e49
3 months, 1 week ago
It's not
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago