An agile project has a documented list of requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.
What should the project manager recommend?
Doladeji
2 months, 1 week agoMonBouj
4 months agovictory108
4 months, 1 week agoprokat_mashin_na_vicecity
4 months, 3 weeks agod370e49
5 months, 1 week agoRayeigh
6 months, 1 week agomatt_joy
6 months, 1 week ago