An agile project has a documented list of requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.

What should the project manager recommend?

  • A. Ask the team to prioritize the high-priority items based on what they feel is a logical sequence to build.
  • B. Ensure the product owner determines the priority based on a product roadmap, release plan, and iteration plan.
  • C. Ask the team to prioritize the high-priority items based on the release plan and what allows for testing most effectively.
  • D. Discard the current categorization of requirements as "high, medium, and low" and prioritize numerically.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
d370e49
1 week ago
Selected Answer: B
I'd go with B. Answer "C" refers to testing which is never even mentioned in the question. Fail.
upvoted 1 times
...
Rayeigh
1 month, 1 week ago
Selected Answer: B
I also think B is correct.
upvoted 3 times
...
matt_joy
1 month, 1 week ago
Selected Answer: B
Ensure the product owner determines the priority based on a product roadmap, release plan, and iteration plan.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...