Exam PMP topic 1 question 1350 discussion

Actual exam question from PMI's PMP
Question #: 1350
Topic #: 1
[All PMP Questions]

A project manager working in a matrix organization manages an internal software development project that is intended to reduce conflicts in the company's internal tracking system. Developers placed the software application in production, and it is currently achieving some benefits. However, the full benefits will not be realized for some time.

What should the project manager do?

  • A. Continue to manage the project until all project benefits are realized.
  • B. Coordinate with the project's functional leads to validate its readiness for transition.
  • C. Request a new project be initiated to monitor and report achievement of the benefits.
  • D. Make updates, mark all project documents as final, and close the project.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Schwery
4 months, 1 week ago
Selected Answer: B
The best course of action is: B. Coordinate with the project’s functional leads to validate its readiness for transition. Explanation: In a matrix organization, the project manager should ensure that the project is ready for transition to operational teams or other responsible parties. This involves collaborating with functional leads to confirm that the software is stable, meets requirements, and is prepared for ongoing management. After validating the transition readiness, the project manager can proceed with project closure and handover responsibilities for benefits realization to the appropriate team.
upvoted 1 times
...
Okstm
5 months ago
Selected Answer: D
Make updates, mark all project documents as final, and close the project.
upvoted 1 times
...
victory108
6 months, 2 weeks ago
Selected Answer: B
B. Coordinate with the project's functional leads to validate its readiness for transition
upvoted 1 times
...
AnhHN11
7 months, 3 weeks ago
Selected Answer: D
B is step is part of the project closure process ( D)
upvoted 1 times
...
Azharmak
8 months, 3 weeks ago
Selected Answer: B
the project manager should coordinate with the project's functional leads to validate its readiness for transition. This approach aligns with best practices in project management, particularly in a matrix organization, and helps ensure sustainable benefits realization.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago