The stakeholders in an agile project are upset because some of the final products do not meet their expectations. When the project manager asks the team about the stakeholders' expectations, the team only mentions the project's objective.
In addition to reminding the team about the importance of stakeholder expectations, interest, and influence in the project, how should the project manager improve this situation?
MonBouj
1 month, 1 week ago6114c29
1 month, 1 week agovictory108
1 month, 1 week agod370e49
2 months, 1 week agoKim222
2 months, 4 weeks agoKim222
3 months, 2 weeks agoIbrahimMZ
3 months, 3 weeks ago