The stakeholders in an agile project are upset because some of the final products do not meet their expectations. When the project manager asks the team about the stakeholders' expectations, the team only mentions the project's objective.
In addition to reminding the team about the importance of stakeholder expectations, interest, and influence in the project, how should the project manager improve this situation?
d370e49
1 week agoKim222
3 weeks, 3 days agoKim222
1 month, 1 week agoIbrahimMZ
1 month, 2 weeks ago