Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 299 discussion

Actual exam question from PMI's CAPM
Question #: 299
Topic #: 1
[All CAPM Questions]

An adaptive project team is grooming the backlog for the next iteration. What does the team need to document in the user stories to determine the work needed to complete each story?

  • A. Team velocity in past iterations
  • B. Related epics of each story
  • C. Detailed acceptance criteria
  • D. Product owner's priorities
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: C
C. Detailed acceptance criteria Explanation: To accurately determine the work needed to complete a user story and ensure everyone understands the requirements, detailed acceptance criteria are essential. They provide clear and specific conditions that must be met for the user story to be considered complete. Team velocity is a metric used to estimate the amount of work a team can complete in a sprint, but it doesn't help define the work for a specific user story. Related epics provide context but don't outline specific tasks. While the product owner's priorities are important for determining the order of work, they don't define the work itself. By having clear acceptance criteria, the team can break down the user story into tasks, estimate effort, and plan the work for the iteration.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...