Exam CAPM topic 1 question 315 discussion

Actual exam question from PMI's CAPM
Question #: 315
Topic #: 1
[All CAPM Questions]

A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?

  • A. Increase quality review cycles.
  • B. Schedule the tasks in sequence.
  • C. Schedule the tasks in parallel.
  • D. Expand the scope of the project.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: C
C. Schedule the tasks in parallel Explanation: To ensure on-time delivery for a small project with time constraints, scheduling tasks in parallel is the most effective approach. This means performing multiple tasks simultaneously, whenever possible, to reduce overall project duration. Increasing quality review cycles might improve quality but would likely extend the project timeline. Scheduling tasks in sequence means doing one task at a time, which is generally less efficient for time-constrained projects. Expanding the project scope would almost certainly increase the project duration, contradicting the goal of on-time delivery. By maximizing parallel work, the project manager can optimize the use of available resources and accelerate project completion.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...