Why the other options are incorrect:
A. Product release plan
➤ Focuses on when and how product increments will be delivered — not on how to introduce new features during the project.
C. Project release plan
➤ Not a standard term in project management. May refer to delivery timelines, but does not address change control or scope modification.
D. Product management plan
➤ This may exist in product-oriented organizations, but in a project management context, changes to scope are governed by the Project Management Plan, not product strategy documentation.
Product Management Plan*
The Product Management Plan typically outlines the strategy, objectives, scope, and features of the product. It provides a detailed roadmap for the product's development, including planned features and enhancements. If a stakeholder proposes a new feature, referring to the Product Management Plan helps in evaluating how the new request aligns with the overall product strategy and objectives. It provides the necessary context for assessing whether the new feature fits within the project scope and aligns with the product's goals
The stakeholder should consult the Product management plan for guidance. This plan outlines the product strategy, features, and priorities, helping guide decisions related to product development and enhancements
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
2 weeks, 2 days ago8a6d137
2 months, 3 weeks ago8a6d137
2 months, 3 weeks agoVangelis_1980
11 months, 2 weeks agovincent8391
8 months ago