Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 330 discussion

Actual exam question from PMI's CAPM
Question #: 330
Topic #: 1
[All CAPM Questions]

During a sprint demo, the customer says that one of the user stories is not ready for customer use. Which checklist should the team look at to find out what has been missed for the user story?

  • A. Definition of done (DoD)
  • B. Burndown chart
  • C. Velocity chart
  • D. Definition of ready (DoR)
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: A
A. Definition of Done (DoD) Explanation: The Definition of Done (DoD) is a checklist of criteria that must be met for a user story to be considered complete. If the customer says the user story is not ready, it means it doesn't meet the agreed-upon DoD. Burndown chart tracks the work remaining in a sprint. Velocity chart measures the team's productivity over time. Definition of Ready (DoR) outlines the criteria for a user story to be ready for development. While DoR is important, it's about getting the user story ready for development, not for customer use. The DoD focuses on the final product and its readiness for the customer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...