Question #: 324
Topic #: 1
[All CAPM Questions]

In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.

Which of the following elements is the team using?

  • A. Definition of done (DoD)
  • B. Burndown chart
  • C. Definition of ready (DoR)
  • D. Backlog refinement
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: A
The project team is using the Definition of Done (DoD) in this scenario. The DoD outlines the criteria that must be met for a deliverable to be considered complete and ready for customer use. By checking off the required criteria on their checklist, the team ensures that the deliverables meet the necessary quality standards and are fit for release.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...