Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 360 discussion

Actual exam question from PMI's CAPM
Question #: 360
Topic #: 1
[All CAPM Questions]

A team is working on a project using an adaptive approach. During project execution, the project gets delayed by one month due to an unforeseen risk.

What should the team do next to deliver this project?

  • A. Reprioritize the work based on the increased visibility of the current risks.
  • B. Accept the project delay and add the risk to the lessons learned document for the next project.
  • C. Stop working on the project completely, even if the team can continue working on the tasks with the identified risk.
  • D. Change the delivery date and deliver the initially agreed-upon scope after mitigation of the identified risk.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
vincent8391
1 week, 5 days ago
Selected Answer: A
Should be A
upvoted 1 times
...
RyeBread
1 month, 3 weeks ago
Selected Answer: A
In an adaptive approach, it’s crucial to reprioritize work based on the increased visibility of current risks to ensure the project stays on track. Therefore, the correct answer is A. Reprioritize the work based on the increased visibility of the current risks.
upvoted 2 times
...
Fav24
1 month, 4 weeks ago
A is the correct answer
upvoted 3 times
...
Vangelis_1980
3 months, 3 weeks ago
Selected Answer: D
D. Change the delivery date and deliver the initially agreed-upon scope after mitigation of the identified risk. Here’s why this option is appropriate: Delivery Date Adjustment: By changing the delivery date, the team acknowledges the impact of the risk and adjusts their timeline accordingly. This allows them to manage expectations and plan for the extended duration. Risk Mitigation: The team should actively work on mitigating the identified risk. This could involve additional efforts, alternative approaches, or contingency plans. The goal is to minimize the risk’s impact on project delivery. Scope Management: Delivering the initially agreed-upon scope ensures that the project remains aligned with its original objectives. The team can focus on quality and meeting stakeholder expectations within the revised timeline. Option D provides a balanced approach, considering both the risk and the project’s overall goals.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...