In an adaptive approach, it’s crucial to reprioritize work based on the increased visibility of current risks to ensure the project stays on track. Therefore, the correct answer is A. Reprioritize the work based on the increased visibility of the current risks.
D. Change the delivery date and deliver the initially agreed-upon scope after mitigation of the identified risk.
Here’s why this option is appropriate:
Delivery Date Adjustment: By changing the delivery date, the team acknowledges the impact of the risk and adjusts their timeline accordingly. This allows them to manage expectations and plan for the extended duration.
Risk Mitigation: The team should actively work on mitigating the identified risk. This could involve additional efforts, alternative approaches, or contingency plans. The goal is to minimize the risk’s impact on project delivery.
Scope Management: Delivering the initially agreed-upon scope ensures that the project remains aligned with its original objectives. The team can focus on quality and meeting stakeholder expectations within the revised timeline.
Option D provides a balanced approach, considering both the risk and the project’s overall goals.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
vincent8391
1 week, 5 days agoRyeBread
1 month, 3 weeks agoFav24
1 month, 4 weeks agoVangelis_1980
3 months, 3 weeks ago