Toward the end of a project, the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?
B
Reviewing the requirements traceability matrix is the most effective action for the project manager in this situation. It ensures that all deliverables are aligned with the specified requirements, helps identify any discrepancies, and facilitates the necessary corrective actions to obtain stakeholder approval.
The quality management plan outlines the quality policies and procedures for the project but does not provide a direct link between specific requirements and the corresponding deliverables.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 month, 2 weeks agofunmis4
2 months, 3 weeks agoRayeigh
3 months, 2 weeks ago9RedFox_JB
3 months, 2 weeks agogaren22
4 months ago