Upon analyzing the report requirements to create a functional design, the project team finds that the information source is not correct and needs to be adjusted. What should the project manager do?
I don't think C is the correct answer. Why would you go straight to a SME without checking the SOW if there's an issue with the information source? I would choose D, "Review".
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
d370e49
1 week ago