Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1361 discussion

Actual exam question from PMI's PMP
Question #: 1361
Topic #: 1
[All PMP Questions]

Upon analyzing the report requirements to create a functional design, the project team finds that the information source is not correct and needs to be adjusted. What should the project manager do?

  • A. Initiate a change request procedure.
  • B. Build a prototype to verify the information.
  • C. Consult with subject matter experts (SMEs).
  • D. Review the statement of work (SOW).
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
d370e49
1 week ago
I don't think C is the correct answer. Why would you go straight to a SME without checking the SOW if there's an issue with the information source? I would choose D, "Review".
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...