Explanation:
A Burndown chart shows the amount of work remaining versus time and helps track how much work has been completed during a sprint or iteration (like a week).
It is commonly used in Scrum and Scrumban to monitor progress and predict whether the team will complete the planned work on time.
Why the other options are incorrect:
A. Gantt chart
A timeline-based chart showing tasks and dependencies — not typically used for tracking weekly completed work in agile teams.
B. Feature chart
Not a standard agile chart; could refer to various things but doesn’t specifically track work done in a timeframe.
C. Kanban chart
Shows work-in-progress and flow of tasks, but does not specifically show the amount completed over time.
A burndown chart is a tool used in agile frameworks, including Scrumban, to visualize the progress of work completed over time. It shows the amount of work remaining versus time, allowing the team to see how much work has been completed within a sprint or a specific time frame. This makes it ideal for understanding what work has been completed during the week.
This chart is specifically designed to show the amount of work completed versus the total work remaining over a specified time period. It's commonly used in Agile methodologies to track progress within a sprint or iteration.
FYI : A Kanban chart is a visual tool used to manage work in progress, but it doesn't focus on completed work.
Explanation:
Burndown Chart: This chart tracks the amount of work remaining in a sprint or project over time. It visually represents the progress made, showing how much work has been completed versus how much is left. It is particularly useful for understanding the team's velocity and whether they are on track to complete their work by the end of the sprint.
Other Options:
A. Gantt Chart: Primarily used for project scheduling, it shows tasks over time but does not specifically indicate completed work in a way that is useful for agile teams.
B. Feature Chart: Typically used to track features in a product backlog, but it may not provide a clear view of completed work in a specific timeframe.
C. Kanban Chart: While it shows the flow of work and the current status of tasks, it may not specifically highlight completed work over a set period like a burndown chart does.
Burndown chart visually represents the work remaining to be completed in a sprint. By looking at the difference between the starting point and the current point on the chart, you can determine the amount of work completed during the week.
Gantt chart is more commonly used in traditional project management and focuses on task dependencies and timelines.
Feature chart is not a standard chart in agile methodologies.
Kanban chart shows the workflow of work items but doesn't explicitly track work completed over a specific period.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
3 days, 15 hours agozvezdo
3 months, 2 weeks agoJtic
7 months agoMonBouj
8 months, 2 weeks agoxenophanes__
8 months, 2 weeks agoRyeBread
9 months, 1 week agoguymartin
11 months, 2 weeks agoVangelis_1980
11 months, 2 weeks agoCyberpleb
11 months, 3 weeks ago