Question #: 150
Topic #: 1
[All PgMP Questions]

Performing quality assurance in a program can result in which one of the following?

  • A. Quality control execution
  • B. Scope fulfillment
  • C. Quality management plan
  • D. Change requests
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
LuanND
2 months ago
Selected Answer: D
Quality assurance involves the continuous monitoring and analysis of quality specifications and standards. When discrepancies or areas for improvement are identified, change requests may be generated to address these issues and ensure that the program meets the required quality standards.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...