At the end of the third iteration, the project team gathers to discuss the stories to be implemented in the next iteration. What should the team do during this session?

  • A. Develop a user story analysis based on the work done, depicting the current status, S-curve, schedule variance (SV), and planned value (PV).
  • B. Run a spike to ensure all information available is correct and then decide which stories to implement.
  • C. Bring up all risks for implementing the user stories and discuss possible solutions.
  • D. Plan the backlog by estimating and reprioritizing the user stories as new information becomes available.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: D
D. Plan the backlog by estimating and reprioritizing the user stories as new information becomes available. Explanation: At the end of an iteration, a team typically gathers to: Review the work completed in the iteration. Inspect the product increment. Adapt the plan for the next iteration.
upvoted 1 times
...
Cyberpleb
2 months ago
Correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...