A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing. Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.
What should the project manager have done to avoid this situation?
Amirov
3 weeks, 5 days agovictory108
1 month, 1 week agoprokat_mashin_na_vicecity
1 month, 3 weeks agoKim222
2 months, 3 weeks agoKim222
2 months, 3 weeks ago9RedFox_JB
3 months, 2 weeks agoAzharmak
3 months, 2 weeks agoAzharmak
3 months, 2 weeks agoFlakyO
4 months, 1 week ago