Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1287 discussion

Actual exam question from PMI's PMP
Question #: 1287
Topic #: 1
[All PMP Questions]

During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?

  • A. Update the project management plan with the new information and inform all of the relevant stakeholders.
  • B. Meet with the stakeholder to better understand their expectations and update the stakeholder engagement plan.
  • C. Invite the stakeholder to all future project review meetings and update the project management plan.
  • D. Add the stakeholder details into the periodic reports and update the project management plan.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Paramak
2 months, 1 week ago
B is the right answer.
upvoted 1 times
...
martinx84
2 months, 1 week ago
Selected Answer: B
Meet with stakeholder
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...