Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1271 discussion

Actual exam question from PMI's PMP
Question #: 1271
Topic #: 1
[All PMP Questions]

The sponsor approaches the project manager with new features they want added to the project. The project is 95% complete, but the sponsor insists that continued support for the project relies on the addition of the new features.

What should the project manager do?

  • A. Implement the new features after assessing the impact.
  • B. Reject the new features since it amounts to gold plating.
  • C. Assess the impact of the features and refer it to the change control board (CCB).
  • D. Add the new features to avoid losing the sponsor's support for the project.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: C
C. Assess the impact of the features and refer it to the change control board (CCB)
upvoted 1 times
...
martinx84
4 months, 2 weeks ago
Selected Answer: C
Assess the impact
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...