Question #: 1098
Topic #: 1
[All PMP Questions]

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

  • A. Consider cultural differences among stakeholders.
  • B. Understand how political aspects can affect the project.
  • C. Schedule communication training for management-level stakeholders.
  • D. Conduct an integration meeting among all stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
4 weeks ago
Selected Answer: A
A. Consider cultural differences among stakeholders
upvoted 1 times
...
Azharmak
4 months, 2 weeks ago
By focusing on cultural differences, the project manager can create a communication plan that respects and incorporates the diverse backgrounds of all team members and stakeholders, thereby enhancing the likelihood of the project remaining on track and achieving its goals.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...