Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1371 discussion

Actual exam question from PMI's PMP
Question #: 1371
Topic #: 1
[All PMP Questions]

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area.

What should the project manager do first?

  • A. Update the risk register
  • B. Update the issue log
  • C. Identify an alternative site
  • D. Issue a change request
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
d370e49
1 week ago
Selected Answer: A
I think A is more appropriate. It's just a risk, not an issue yet (at least nothing of that sort is implied in the question)
upvoted 1 times
...
Kim222
1 month, 1 week ago
Selected Answer: A
A is risk
upvoted 1 times
...
c8ee0e6
2 months, 2 weeks ago
Selected Answer: A
Option B says - Update the issue log: The issue log is used to track and manage issues that have already occurred or are currently affecting the project. The discovery of the government-owned area is a risk rather than an issue that has already manifested. Updating the risk register (Option A) is the most appropriate initial action for the project manager in response to discovering that the location for the storage and distribution facility is a government-owned area. This ensures that the project team is aware of the risk, can plan accordingly, and can communicate effectively with stakeholders about potential impacts and mitigation strategies.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...