A bridge construction project has been paused due to a political change in the local government. After almost 5 years, the new government would like to resume the project, and a project manager is assigned.
What should the project manager do first?
A.
Prepare an estimate of the time and cost to complete this project.
B.
Study the project's lessons learned to understand why it was paused.
C.
Meet the new stakeholders and understand their expectations.
D.
Examine the project's business case in order to resume the project.
The question says first thing and as per the choices, the PM will need to understand the new stakeholder's expectations.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 month, 1 week agoc8ee0e6
4 months, 2 weeks ago