A.
It is a matrix that identifies who must communicate with whom.
B.
It is a matrix that documents the stakeholders' requirements, when the requirements were created, and when the fulfillment of the requirements took place.
C.
It is a matrix that documents stakeholders' threats, perceived threats, and communication needs.
D.
It is a matrix that identifies all of the stakeholders and to whom they must report to.
C is correct
This matrix helps in understanding each stakeholder's potential impact on the project, their concerns or threats, and how to effectively communicate with them to ensure their needs and concerns are addressed.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
tungdt
5 months, 3 weeks ago