What project management term would you associated with a predetermined budget you're your program?

  • A. Program governance
  • B. Constraint
  • C. Cost baseline
  • D. Assumption
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
tungdt
9 months, 1 week ago
C is correct answer. The project management term associated with a predetermined budget for your program is Cost Baseline.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
AI-102
Chicago, 1 minute ago