Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1308 discussion

Actual exam question from PMI's PMP
Question #: 1308
Topic #: 1
[All PMP Questions]

A project manager has taken over an existing project. According to the previous project manager, the project is on track and within budget. However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

  • A. Schedule a meeting with the previous project manager.
  • B. Submit a change request to the change control board (CCB).
  • C. Schedule training for project team members.
  • D. Conduct an earned value analysis (EVA).
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: D
D. Conduct an earned value analysis (EVA)
upvoted 1 times
...
martinx84
4 months, 3 weeks ago
Selected Answer: D
Conduct EVA
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...