Exam PgMP topic 1 question 63 discussion

Actual exam question from PMI's PgMP
Question #: 63
Topic #: 1
[All PgMP Questions]

A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent $620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario?

  • A. Schedule, because the program's planned value is only $700,000.
  • B. Cost, because the program has a cost variance of -7,500
  • C. Schedule, because the program has a schedule performance index of .88.
  • D. Cost, because the program has an estimate to complete of $1,151,429.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
10 months ago
C is correct answer BAC = 1750000, AC = 620000 EV = 0,35 x 1750000 = 612,5 CPI = EV/AC = 612,5/620000 = 0,98175 PV = 0,4 x BAC = 0,4 x 1750000 = 700 SPI = EV/PV = 612,5/700 = 0,875 =0,88
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago