Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?

  • A. Quality Management System
  • B. Change Control System
  • C. Project Management Information System
  • D. Integrated Change Control System
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AmrKHALIL
1 month ago
Selected Answer: C
C. Project Management Information System
upvoted 1 times
...
tungdt
5 months, 4 weeks ago
C is right answer The system considered the parent of the change control system documented in Donna's plan is the Project Management Information System (PMIS). The PMIS provides the overarching framework and tools for managing all aspects of the project, including the change control system. This system ensures that changes are properly documented, tracked, and reviewed before decisions are made regarding their approval or decline.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago