Exam CAPM topic 1 question 353 discussion

Actual exam question from PMI's CAPM
Question #: 353
Topic #: 1
[All CAPM Questions]

An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.

Which two of the following items should be included in the planning? (Choose two.)

  • A. Sprint backlog
  • B. Increments
  • C. Daily scrum
  • D. Sprint retrospective
  • E. Sprint review
Show Suggested Answer Hide Answer
Suggested Answer: AB 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month ago
Selected Answer: AE
A. Sprint backlog E. Sprint review the two items that should be included in the planning are the sprint backlog and the sprint review. These artifacts play a critical role in managing the work and ensuring that the team remains aligned with stakeholder expectations throughout the project.
upvoted 1 times
...
glatovi
1 month, 1 week ago
Selected Answer: AB
Others are sprint events.
upvoted 1 times
...
Fav24
1 month, 4 weeks ago
Sprint Retrospective is an event, not an artifact so it cannot be the right answer, Instead Increments which is a summation of completed work during a sprint
upvoted 2 times
...
flee
5 months ago
Selected Answer: AD
Tricky question, but the answers should have been A and D, as they are the only two artifacts directly relates to planning that should be included in initial kickoff meeting for project management planning. Here's the reasoning: Sprint backlog (A): This is an essential artifact in Scrum methodology. It represents the list of tasks that the team plans to complete during the sprint. It helps in defining what work will be done during the sprint and is crucial for planning and tracking progress. Sprint retrospective (D): This is a meeting that occurs at the end of each sprint where the team reflects on the past sprint and identifies what went well and what could be improved. It is an important part of the agile process to continuously improve the team's performance.
upvoted 1 times
flee
5 months ago
The other options: Increments (B): While important, increments refer to the sum of all the completed product backlog items at the end of a sprint. It's a result rather than a planning artifact. Daily scrum (C): This is a daily meeting during the sprint where the team synchronizes activities and plans for the next 24 hours. It is not part of the initial planning phase but occurs daily during the sprint. Sprint review (E): This is a meeting held at the end of the sprint to review the increment and get feedback. It is not part of the initial planning phase but occurs at the end of each sprint.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...