A few months into a project, several schedule issues have emerged. Drag the schedule problems on the left to the specific tools on the right that, if implemented during schedule development, could have prevented the issues.

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Schwery
1 month ago
Incomplete or incorrect activity dependencies -> Precedence diagrammin method Unrealistic activity duration -> Parametricssessment Incorrect Secuencing -> Critical Path Missing activities -> Decomposition
upvoted 1 times
...
victory108
1 month, 2 weeks ago
Incomplete or incorrect activity dependencies --> Precedence diagramming method Missing activities --> Decomposition Incorrect sequencing --> Critical path method Unrealistic activity durations --> Parametric Assessment
upvoted 1 times
...
Testeryrb
2 months, 1 week ago
Parametric Assessment ---> Unrealistic activity duration Precedence diagramming method ---> Incomplete or incorrect activity dependencies Decomposition ---> Missing activities Critical path method ---> Incorrect sequencing
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...