Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1281 discussion

Actual exam question from PMI's PMP
Question #: 1281
Topic #: 1
[All PMP Questions]

A project manager is reviewing the lessons learned for an historical project. The review identifies that the client's engineer was adamant that they review all changes, even those not identified in the contract.

How should the project manager deal with this when planning the project?

  • A. Update the project charter with this information regarding change management.
  • B. Talk with the client to ensure they are aware of the change management procedure.
  • C. Ensure the change management plan highlights this requirement to prevent future issues.
  • D. Update the project risk register to identify this risk and describe how to mitigate the issue.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: B
B. Talk with the client to ensure they are aware of the change management procedure
upvoted 1 times
...
Anitak
5 months, 1 week ago
The answer should be D not C.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...