Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1343 discussion

Actual exam question from PMI's PMP
Question #: 1343
Topic #: 1
[All PMP Questions]

A client comes to the company asking to copy a project that was executed 2 years ago in the same city, with the expectation that the new project will have the same cost and duration. While finalizing the project management plan, the project manager realizes that the baseline costs are much higher than the original project.

What could the project manager have done to avoid this?

  • A. Assigned the same project resources to this project
  • B. Determined a budget reserve for this project
  • C. Verified applicable budget inputs related to this project
  • D. Estimated a budget for the project's quality management
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: C
C. Verified applicable budget inputs related to this project
upvoted 1 times
...
tonybuivannghia
3 months, 2 weeks ago
Selected Answer: C
C is correct
upvoted 1 times
...
9RedFox_JB
3 months, 2 weeks ago
By verifying applicable budget inputs related to the project, the project manager can ensure that the cost estimates are accurate and reflect current conditions. This proactive approach helps in setting realistic project expectations and avoids discrepancies between planned and actual costs.
upvoted 2 times
...
omankoman
5 months ago
Selected Answer: C
C is the answer. Prioritize options Evaluate and analyze the problem to determine root cause Review the plan Hold meetings
upvoted 1 times
...
LongNH2904
5 months, 1 week ago
Selected Answer: B
To avoid the situation where the baseline costs of a project are much higher than expected, the project manager could have taken the following action: B. Determined a budget reserve for this project. Here’s why this option is the most appropriate: Budget Reserve: A budget reserve, also known as contingency reserve, is set aside to cover unforeseen costs and risks that may arise during the project execution. By determining a budget reserve upfront, the project manager can account for potential cost overruns or unexpected expenses that may not have been anticipated when baselining the project. Managing Uncertainty: Projects inherently involve uncertainty, and even if the new project is a replication of a previous project, various factors could lead to cost variations over time (e.g., inflation, changes in resource costs, availability of materials). A budget reserve helps in managing this uncertainty by providing a cushion against cost increases.
upvoted 1 times
d370e49
2 months, 1 week ago
That's a long explanation to justify a wrong answer! The correct answer is C. Budget input are important here, because it's based on previous projects. A budget reserve doesn't even matter in this case.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...