Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 322 discussion

Actual exam question from PMI's CAPM
Question #: 322
Topic #: 1
[All CAPM Questions]

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

  • A. Bottom-up
  • B. Three-point
  • C. Parametric
  • D. Analogous
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Fav24
2 months ago
Analogous estimating is particularly useful in the early stages of a project when detailed information is not yet available. It's often used for initial budgeting, timeline projections, or when there's a need for a quick estimate.
upvoted 1 times
...
Vangelis_1980
3 months, 4 weeks ago
Selected Answer: D
The answer is: D. Analogous Explanation: Analogous estimating relies on historical data from similar projects to estimate the cost of a new project. By comparing the current project to past projects, the project manager can develop a cost estimate based on those previous figures. Let's briefly review the other options: Bottom-up estimating involves breaking down a project into its smallest components and estimating the cost of each, then summing them up for a total project cost. Three-point estimating involves creating an optimistic, pessimistic, and most likely estimate for each project activity. Parametric estimating uses statistical models based on historical data and project parameters to estimate costs. While it uses historical data, it differs from analogous estimating as it involves statistical modeling and parameters. Since the prompt explicitly mentions using historical data from a previous project, analogous estimating is the most fitting choice.
upvoted 2 times
...
Andrew_1980
4 months, 3 weeks ago
Selected Answer: C
Nothing is said about the similarity of the project completed. So 'Analogous' can't be chosen.
upvoted 2 times
...
GoldenRetriever
5 months, 1 week ago
Selected Answer: C
Answer C is based on Historical data
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...