A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and delay new feature development.
Which action should the project manager take to resolve the quality issues?
A.
Discuss adding business scenario tests with the customer.
B.
Discuss adding additional test cases with the product owner.
C.
Add more test scenarios based on the issues found.
D. Plan for continuous validation of the product.
Planning for continuous validation helps ensure that quality is built into the product development process from the start. It allows for ongoing assessment and verification at every stage, reducing the risk of major issues being discovered after delivery. This approach aligns with agile practices and ensures that issues are detected early and addressed promptly, preventing delays in future feature development.
Proactive vs. Reactive Approach
Option C: Adding more test scenarios based on the issues found is a reactive measure. It focuses on addressing the specific problems identified after they have already caused rework and delays. This approach might solve the current issues but doesn't necessarily prevent future problems.
Option D: Continuous validation is a proactive approach. It involves regularly checking and validating the product throughout its development. This helps to identify and address potential issues early and continuously, preventing significant problems from accumulating and causing delays.
B. Discuss adding additional test cases with the product owner.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 month, 1 week agoNgho
1 month, 3 weeks agoomankoman
5 months agoLongNH2904
5 months, 1 week agoPmpjune152024
5 months, 2 weeks ago