Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 445 discussion

Actual exam question from PMI's CAPM
Question #: 445
Topic #: 1
[All CAPM Questions]

A backwards path calculation estimates that the last work package will be completed 24 days from this coming Monday. The scrum team operates in two-week sprints.

How many sprints are needed to complete the work?

  • A. 2
  • B. 1.5
  • C. 3
  • D. 2.5
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: A
Two-week sprints are 10 working days. Number of sprints = Total days / Days per sprint --> 24/10 = 2.4. So the closest round number is 2.
upvoted 1 times
...
Andrew_1980
2 months, 2 weeks ago
Selected Answer: A
Sprints can be measured as Integers only. So 1.5 & 2.5 are incorrect answers. If sprint = 14 days, then 24 will be covered in 2 sprints
upvoted 1 times
Vangelis_1980
1 month, 3 weeks ago
Correct but keep in mind that two-week sprints are 10 working days. Number of sprints = Total days / Days per sprint --> 24/10 = 2.4. So the closest round number is 2.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...