Question #: 1075
Topic #: 1
[All PMP Questions]

A product is undergoing its last iterative increment, and the project team is ready to make the final deployment. The company’s financial manager is asking the project team to complete the deployment and close the project as soon as possible so it can be capitalized.

What should the project manager do?

  • A. Expedite the final deployment and close the project.
  • B. Ignore the stakeholder's request as there is a defined plan.
  • C. Update the acceptance criteria for the iteration.
  • D. Check on the definition of done (DoD) for the project.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
4 weeks, 1 day ago
Selected Answer: D
D. Check on the definition of done (DoD) for the project
upvoted 1 times
...
Pmpjune152024
5 months, 2 weeks ago
Selected Answer: D
In this situation, the project manager should check on the definition of done (DoD) for the project (option D). The definition of done outlines the criteria that must be met for the project to be considered complete, ensuring that all necessary deliverables and quality standards are met before the project is closed.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...