An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.

Which two of the following elements should be included? (Choose two.)

  • A. Sprint backlog
  • B. Increments
  • C. Product backlog
  • D. Sprint retrospective
  • E. Daily scrum
Show Suggested Answer Hide Answer
Suggested Answer: DE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Fav24
2 months ago
D and E
upvoted 2 times
...
Andrew_1980
4 months, 3 weeks ago
Selected Answer: DE
Events are Retro & Daily scrum
upvoted 3 times
...
1wheel
5 months, 3 weeks ago
Selected Answer: AC
In an adaptive project management approach, several artifacts play a crucial role in keeping the project aligned with requirements and business goals. Let’s explore two key artifacts: Product Backlog: This dynamic list captures all desired features, enhancements, and changes requested by stakeholders. It evolves throughout the project, allowing the team to prioritize and adjust based on changing needs. Sprint Backlog: During each sprint (iteration), the team selects items from the product backlog to work on. The sprint backlog contains specific tasks, user stories, and acceptance criteria for that sprint. It ensures transparency and guides the team’s work.
upvoted 2 times
Andrew_1980
4 months, 3 weeks ago
The key word is EVENT. Retro & Daily are events
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...