A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?
A.
Set performance standards and direction.
B.
Hold early kick-off meetings and regular weekly meetings.
C.
Select members for their skill or potential.
D.
Establish the project scope and set clear team objectives.
I strongly believe its D. I also confirmed with GPT - Establishing the project scope and setting clear team objectives provides a foundation for all subsequent activities. It ensures that every team member understands what needs to be achieved and what their role is in achieving it. This clarity is essential for forming a cohesive, high-performing team. It aligns everyone's efforts towards common goals and helps in planning, coordination, and setting performance standards effectively.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 month, 3 weeks agopasspmponetime
2 months, 1 week agoKim222
2 months, 4 weeks ago27b2ada
3 months, 1 week agoc8ee0e6
4 months, 2 weeks agoELTIGANI
5 months, 3 weeks ago